Everything that can travel should be proved before it travels

Factory acceptance and site acceptance test different things, and most contracts blur them into one word called acceptance. The blur is where the argument starts, because a cell that passed in the factory and fails on site has not failed twice.

Sheet
01 of 08
Lane
FAT / SAT
Sections
10
Points
12
Issue
Issue 24
Filed
2026-11-24
Factory acceptance and site acceptance test different things, and most contracts blu
Sheet 01 · fat / sat

Two tests, two questions

The factory acceptance answers whether the cell does what the specification says when it is built and wired in a place where the builder controls everything. The site acceptance answers whether the cell does it in the building where it has to live.

Those are different questions and they are answered by different evidence. The factory test can measure cycle time on a perfect floor with a perfect part supply. The site test can only confirm that the measurements survive the move, the foundation and the services.

So a contract that says acceptance happens after installation has collapsed two milestones into one, and it has given away the lever that the factory test provides. A defect found in the factory is a builder's cost. The same defect found on site is a schedule problem with two parties.

The practical arrangement is two named tests with two named acceptance criteria, and a clause that says what happens when the second one fails after the first one passed.

What belongs in the factory test

The factory test should carry everything that is independent of the building: the sequence, the interlocks, the program, the fixture, the tool path, the cycle time under a defined part supply and the weld or cut quality on sample parts.

It should also carry the things that are expensive to change later: the safety logic, the guard openings, the light curtain positions, the control architecture and the data the cell reports to whatever sits above it.

The end of arm tooling belongs there too, because the tool's reach and its collision envelope are easiest to prove when the cell is still at the builder's. A tool that collides with a guard on site was a tool that was never run through its full envelope.

And the documentation belongs there: the drawings, the program backup, the parameter list and the spare parts list should be delivered at the factory test rather than promised at handover.

What can only be proved on site

Four things can only be proved on site, and the list is short enough to remember. The foundation and the levelling. The incoming services: power quality, air pressure and flow, gas purity, water temperature and flow. The interface to whatever the cell connects to upstream and downstream. The behaviour of the building's own services, including extraction and any interlocked fire signal.

Each of those four is a property of the building rather than of the cell, which is why no amount of factory testing can cover them. A cell that passed at the builder's and trips on site at the first weld is usually reporting a voltage sag or an air pressure drop.

The site test should therefore be built around measurement of the four rather than around repetition of the factory test. Repeating the factory test on site proves that the move did not break anything, which is worth knowing but is not the same thing.

A site test that is a copy of the factory test will pass and the cell will still fail in production, because the four building conditions are not in it.

The utilities survey belongs before the order

The single most effective document in an integration project is the utilities survey, and it should be done before the purchase order rather than after the shipment. It records the actual power capacity at the panel, the actual air pressure at the drop, the gas supply route and the floor's flatness over the cell's footprint.

A survey that finds a shortfall before the order produces a project change. The same finding after installation produces a delay and a claim, because the cell is on site and the fix is a building modification.

The survey should state measured values rather than nameplate values. A panel rated for a current that the actual supply cannot deliver is a panel that will trip the cell at the first multi axis move.

The cost of the survey is a day of an engineer's time. The cost of skipping it is the difference between a change order and a dispute, and that difference is usually the whole margin on the integration.

The part supply assumption

Cycle time is always quoted against a part supply, and the part supply is the assumption that most often fails to survive the project. A cycle time proved with a full buffer and a perfect orientation is a cycle time that the real line may never reproduce.

The factory test should state the supply conditions: the buffer level, the orientation method, the interval between parts and the reject handling. Without those four, the cycle time figure is a number without a meaning.

The site test should reproduce the supply conditions rather than the cycle time. If the site can deliver parts at the stated interval and the cell meets the stated cycle, the cell is accepted. If the site cannot deliver at that interval, the cell has met its specification and the line has not.

That distinction is what keeps an integration argument from becoming a dispute about whose number is wrong. The cell's number is right against its assumption, and the assumption is a document.

Punch lists and the definition of done

A punch list is the mechanism that lets a project close without pretending it is finished. It records the items that are incomplete, who owns each and the date by which it will be closed.

The list should distinguish three kinds of item: defects where the cell does not meet specification, omissions where something specified was not supplied, and observations where something works but should be improved. Mixing the three in one list is how a punch list becomes an argument.

The definition of done should be written before the list exists, because the definition is what decides which items belong on it. A definition of done that is written after the punch list is a definition that has been negotiated backwards from the defects.

Retention is the financial mechanism that gives the list weight. A held percentage released on closure is what makes the list a schedule rather than a wish.

The witness and the record

Every acceptance test needs a witness who is entitled to sign, and the signature has to be against a criterion rather than against an impression. A witness who signs a page that says the cell performs as specified has signed nothing that can be checked later.

The record should carry the measured value, the instrument, the date and the condition under which the measurement was taken. A cycle time recorded without the part supply condition is a number that cannot be defended.

Photographs and videos belong in the record, particularly for the safety items and for the guard openings. A photograph of an interlock test is worth more than a paragraph describing it.

The record should be delivered as one file rather than as a folder of photographs, because the file is what gets read at the warranty claim and the folder is what gets lost.

Retesting after a change

Any change after the factory test invalidates the parts of the test it touches, and the invalidation has to be scoped rather than assumed. A program change invalidates the cycle time and the weld quality. A guard change invalidates the safety logic and the access test.

The scope should be a table with the change in one column and the tests to be repeated in another, agreed before the change is approved. Without the table, every change produces either a full retest that costs a week or no retest at all.

Changes made on site are the ones most likely to skip retesting, because the schedule pressure is highest there and the person making the change is often the person who would have to run the test.

The table is a small document that prevents a large argument. It should name who decides that a retest is complete, because a retest without a closure decision becomes a permanent open item.

Where the money sits in the two tests

The factory test costs the builder a week of floor space and an engineer, and it saves the project the cost of discovering defects in a building that is already full of other trades. That trade is almost always favourable and it is almost always skipped when the schedule is tight.

The site test costs the integrator a week on site, which is the most expensive week in the project, and it saves the project the cost of a cell that runs at eighty percent of its specified rate for a year before anyone proves it.

Both tests are cheap relative to the failures they prevent, and both are cut first when the schedule slips. The cutting is a decision that trades a known cost for an unknown one, and it should be made explicitly rather than by default.

The contract is where the explicitness lives. A contract with two named tests and two named criteria makes the cut a variation. A contract with one word called acceptance makes the cut invisible.

The five documents that close a project

The as built drawings, the program and parameter backup, the test record, the punch list closure and the training record. Five documents, each of which answers a question that will be asked within the first year.

The drawings answer what was actually installed, which matters when a part fails and the schematic in the manual does not match the panel. The backup answers how to restore the cell after a controller loss.

The test record answers whether the cell ever met its specification, which matters at the first performance argument. The punch list closure answers whether the outstanding items were done. The training record answers whether the operators were ever taught, which is the answer to most first year downtime.

A project that closes without the five has closed on the invoice rather than on the handover, and the difference appears in the second year when nobody can answer any of the five questions.

The cell this note keeps returning to is a robot welding system scoped like this one, where the two tests are named separately in the contract rather than merged into a single milestone.

Acceptance points12
  • Name two tests with two sets of criteria in the contract rather than one word called acceptance.
  • Put sequence, interlocks, program, tooling and tool path envelope into the factory test.
  • Deliver drawings, program backup, parameter list and spare parts at the factory test.
  • Build the site test around foundation, services, interfaces and building systems.
  • Measure utilities before the purchase order rather than nameplate values.
  • State the part supply assumption beside every cycle time figure.
  • Reproduce the supply conditions on site rather than repeating the cycle time test.
  • Separate defects, omissions and observations on the punch list.
  • Write the definition of done before the punch list exists and tie retention to closure.
  • Record measured value, instrument, date and condition for every accepted figure.
  • Scope retests with a change to test table agreed before the change is approved.
  • Close the project on the five documents, not on the invoice.