IHIntegration Handover Notes
Issue 24  /  acceptance & handover2026-11-24
Issue 24  ·  filed 2026-11-24

The part that gets signed is the part nobody tested.

Eight sheets on the part of an integration project that decides whether it was worth doing: what is proved in the factory and what can only be proved in the building, how a collaborative cell is measured, how a fixture is accepted for a thousand cycles rather than one, and why a changeover time is a stopwatch reading.

08Sheets
78Sections
96Points
1Signature

Contents

sheer number · lane · sections · points
01
FAT / SAT

Everything that can travel should be proved before it travels

Factory acceptance and site acceptance test different things, and most contracts blur them into one word called acceptance. The blur is where the argument starts, because a cell that passed in the factory and fails on site has not failed twice.

10 sect
12 pts
02
Safety

A cobot is accepted on how fast it stops, not on whether it stops

Collaborative operation is a set of measured limits rather than a feature. The acceptance question is whether the cell stays inside those limits when a person walks into the space at production speed, and that is a test rather than a statement.

10 sect
12 pts
03
Fixture

A good first article proves the fixture once, not a thousand times

The first part off a new fixture is measured and signed, and the signature becomes the evidence that the fixture works. The evidence that matters is the drift of the hundredth part, and that number is not on the sheet.

10 sect
12 pts
04
Enclosure

A laser enclosure is accepted on its interlocks, not on its height

Enclosure height is the visible part of laser safety and it is the part that is easiest to get right. The part that fails audits is the interlock chain, because a chain is only as good as its weakest link and every link has a bypass.

10 sect
12 pts
05
Cycle

Cycle time is proved on the slowest part, not on the average one

A cycle time quoted as an average describes a cell that has already been running for a year. The number that decides whether the cell pays for itself is the one on the part that fights back, and that part is in every batch.

09 sect
12 pts
06
Trajectory

Five axes are accepted on posture, not on position

A three axis machine is judged by where the tool is. A five axis machine has to be judged by how the tool is oriented while it gets there, and that is a different measurement with a different failure mode.

09 sect
12 pts
07
Changeover

Changeover time is a measurement, never a promise

A changeover quoted in minutes is a changeover that has been described by the person who designed the fixture. The number that matters is the one an operator with cold hands produces on the second shift, and it only exists if someone put a stopwatch on it.

10 sect
12 pts
08
Handover

A handheld system is accepted in the operator's hands, not in the report

There is no axis accuracy to measure and no cycle time to prove. The acceptance for a handheld tool is whether a trained operator produces a consistent weld at the end of a shift, and that is a trial rather than a test.

10 sect
12 pts