Changeover time is a measurement, never a promise

A changeover quoted in minutes is a changeover that has been described by the person who designed the fixture. The number that matters is the one an operator with cold hands produces on the second shift, and it only exists if someone put a stopwatch on it.

Sheet
07 of 08
Lane
Changeover
Sections
10
Points
12
Issue
Issue 24
Filed
2026-11-24
A changeover quoted in minutes is a changeover that has been described by the person
Sheet 07 · changeover

The definition decides the number

Changeover time runs from the last good part of the previous variant to the first good part of the next. That definition includes the unload, the fixture change, the program recall, the first article check and the adjustment that follows it.

Most quoted changeover times exclude one or more of those five, and the exclusion is usually the first article. A changeover quoted without the first article is a changeover quoted to the point where the uncertainty begins.

The scope should be written before the number is quoted, because a changeover of ten minutes with a first article and a changeover of four minutes without one are both true and neither is comparable.

The acceptance should therefore state the scope and measure the number against it, and the contract should use the same scope so that the two numbers can be compared.

Internal and external work

The single most effective changeover improvement is moving work from internal to external, which means doing it while the machine is still running rather than after it stops. The tooling, the program and the fixtures for the next variant are prepared during the previous variant's cycle.

A worktable cell has a limited set of external tasks: the fixture can be pre assembled off the table, the program can be pre selected, the part can be pre loaded onto a second table if the cell has one.

A cell with two tables can change over in the time of a table swap rather than in the time of a fixture change, and that is a structural difference rather than a procedural one. The acceptance should state which structure was bought.

Cells with one table depend on the external preparation being done, which means the changeover number is a property of the operating procedure rather than of the machine.

The accuracy cost of speed

Quick change mechanisms buy speed with tolerance, and the tolerance shows up as a changeover error that needs a first article adjustment. A mechanism with a repeatability of a few hundredths of a millimetre needs no adjustment for a coarse process and needs one for a tight seam.

The trade is therefore not free: a changeover that saves ten minutes and adds an adjustment of five is a net saving only if the adjustment is inside the first article step rather than in addition to it.

The acceptance should measure both the changeover time and the changeover error, because the second is what decides whether the first is a saving.

A cell with a fast changeover and a large changeover error is a cell that appears to change over quickly and spends the time in the adjustment instead.

Program recall and parameter sets

A program recall is fast when the program is a single file and slow when the program is a set of files that have to be loaded in order. A cell with a hundred variants and a manual load sequence has a changeover time that grows with the library.

The parameter sets have a similar problem: the weld parameters live in a table indexed by variant, and the table has to be selected rather than the variant's file opened. A table that is selected by the program is a table that cannot be wrong.

The acceptance should test a recall from the least recently used variant rather than from the one that was just running, because the least recently used is the one where the file path or the name has drifted.

The recall test is also a check on the naming convention, and a naming convention that has drifted is the source of the wrong program being run on a part.

The first article is part of the changeover

The first article check is the step that confirms the changeover worked, and it belongs inside the changeover time because it is inside the machine's unavailability.

The check should be a measurement of the feature the variant's tolerance controls, taken with an instrument that the operator can use at the machine. A check that requires the quality lab is a check that takes the machine out of service for longer.

The acceptance should state the check method and the acceptance limit, because a check without a limit is an inspection rather than a decision.

A cell with an in process measurement can fold the check into the cycle, and that changes the changeover definition again. The acceptance should state whether the check is in the cycle or after it.

Measuring it with a stopwatch

The measurement is a stopwatch on the two defined events, taken by someone who is not the person performing the changeover, over at least three cycles. Three cycles because the first is the learning cycle and the third is the settled cycle.

The record should carry each cycle's time separately, because the three times describe the learning curve and the curve is what the production planner needs.

The settled cycle's time is the number to quote. The first cycle's time is the number that a supervisor will see on the first day of a new variant, and both are true and they answer different questions.

The stopwatch should be visible rather than concealed, because a concealed timing measures a performance and a visible timing measures a process. The acceptance wants the process.

The matrix rather than the average

A cell with four variants has twelve changeover pairs, and each pair has its own time. An average over the twelve describes a changeover that no operator will ever perform.

The acceptance should measure so that the matrix can be filled, which in practice means measuring the pairs that production will use most rather than all twelve. The pairs chosen should be the high runners and the worst case.

The worst case pair is usually the one that differs in the most dimensions: a different fixture, a different program, a different parameter set and a different first article instrument. That pair is the number to quote when someone asks what the cell can do.

The matrix belongs in the cell's file and it belongs in the production plan, because the plan's batch sizes are derived from it.

Changeover and the overall equipment measure

The changeover time enters the equipment measure through the availability term, and the way it enters is by the number of changeovers rather than by their duration. A cell that changes over twenty times a shift loses more than a cell that changes over twice.

That means the batch size decision and the changeover time are the same decision, and a cell with a four minute changeover can run small batches while a cell with forty cannot.

The acceptance should therefore state the changeover time and the batch size at which it was measured, because a changeover measured on a batch of one is a changeover measured in the worst case.

A cell quoted for small batch production should be accepted on small batch production, and a cell quoted for large batches should not be measured on small ones.

Where the promise comes from

A changeover promise comes from the designer's estimate of the tasks, and the estimate is usually right about the tasks and wrong about the interruptions. The interruptions are the phone call, the missing tool, the part that is not where it should be.

The acceptance measurement includes the interruptions if it is taken in production conditions, and excludes them if it is taken in a demonstration. The difference between the two is the difference between a promise and a number.

The practical compromise is to measure in demonstration conditions and to state that the figure excludes interruptions, with a separate allowance for them in the plan.

Either approach is defensible as long as the scope is written. The indefensible approach is to quote the demonstration number and let the plan assume it is the production number.

The four things to accept on a worktable

The changeover time with a stated scope. The changeover error measured across the same changeover. The recall test from the least recently used variant. The first article method and its limit.

Four items, all measurable in an afternoon, and all four belong in the cell's file because they are the numbers that the production plan will be built on.

The three axis worktable laser welding machine described in this note is the case where the table is the changeover mechanism, and its acceptance is the four items above rather than the axis accuracy alone.

A cell accepted on the four can be planned against. A cell accepted on an axis figure and a promise can be planned against a hope, and the difference appears in the second quarter's output.

The cell where the table is the changeover mechanism is the three axis worktable laser welding machine described in this note, and its acceptance is four items rather than an axis figure.

Acceptance points12
  • Define changeover from last good part to first good part and write the scope down.
  • State whether the first article check is inside the changeover time.
  • Move tooling, programs and fixtures to external work where the structure allows.
  • State whether a second table was bought, because it changes the structure.
  • Measure the changeover error as well as the changeover time.
  • Test a recall from the least recently used variant, not the last one run.
  • Put the program and parameter recall behind the variant selection rather than a manual load.
  • Time at least three cycles and record each separately.
  • Quote the settled cycle and keep the first cycle for the supervisor's expectation.
  • Use a visible stopwatch and a timer who is not the operator.
  • Fill the changeover matrix for high runners and for the worst case pair.
  • State the batch size at which the changeover was measured.